Russian Standard Tour 2010
- 5 to 10 events in 2010
- 1 day: set-up, event, dismantling
- 1 project manager: detailed and comprehensive planning, preparation, coordination and
- implementation of the entire tour
- Creation and construction of all event equipment (bar/back board/dance floor)
- Recruitment, supervision and briefing of hostess
      
Street Parade 2009
- Assembly: artist zone, public stages, Partysan Boat
- 3 project managers, 18 employees
- 3 days, 700 working hours
- 6 hours setting up 30 public stages
- 30 journeys, 450 m3 of equipment
  
Samsung Road Show 2008
- Assembly of show containers
- Conversion, tool development according to the set theme
- 1 project manager, 3 employees
- Operation in 6 cities, each for one week
  
Red Bull Air Race 2007
- 5 project managers, 30 employees
- Days, 1,800 working hours
- 18 articulated trucks, 1,000 m3 of equipment
- Assembly: public area, race club, media centre, pilots’ area, High Flyer Lounge
  
|